The regulatory period for the first default price-quality path ran from 1 July 2013 to 30 September 2017.

Businesses affected by the 2013–2017 default path:

  • Distribution

    • GasNet Limited
    • Powerco Limited
    • Vector Limited
  • Transmission

    • Maui Development Limited
    • Vector Limited

This view shows the latest stage in the project. Click on the circled dates to see details. Navigate to other months, or scroll down, to see all stages.

Note: these dates are indicative only and are subject to change.

  • 27 Mar 2014

    Completed

    Gas transmission services default price-quality path determination 2013

    See documents

  • 29 May 2013

    Completed

    Feedback received on process to set default price-quality paths

    See documents

  • 23 Apr 2013

    Completed

    Feedback on process for setting the default price-quality paths

    See documents

  • 28 Feb 2013

    Completed

    Final decision on the default price-quality paths for gas pipeline services

    See documents

  • 19 Feb 2013

    Completed

    Submission on technical consultation for the default price-quality paths for gas pipeline services

    See documents

  • 08 Feb 2013

    Completed

    Update paper and technical drafting of determinations proposed for the default price-quality paths

    See documents

  • 11 Jan 2013

    Completed

    Cross-submissions on revised gas draft decision on default price-quality paths

    See documents

  • 10 Dec 2012

    Completed

    Submissions on revised gas draft decision on default price-quality paths

    See documents

  • 24 Oct 2012

    Completed

    Revised gas draft decisions on default price-quality paths

    See documents

  • 15 Aug 2012

    Completed

    Information requests for setting of default price-quality paths

    See documents

  • 15 Aug 2012

    Completed

    Correspondence outside of draft decisions consultation process

    See documents

  • 20 Jun 2012

    Completed

    Process update for DPPs for electricity and gas

    See documents

  • 29 Feb 2012

    Completed

    Initial DPP – Commencement date deferral

    See documents

  • 14 Feb 2012

    Completed

    Submissions on Initial DPP – Commencement date deferral

    See documents

  • 03 Feb 2012

    Completed

    Initial DPP – Commencement date deferral – Draft decision

    See documents

  • 30 Jan 2012

    Completed

    Cross-submissions initial draft price-quality path GPBs draft reasons

    See documents

  • 20 Dec 2011

    Completed

    Submissions initial draft price-quality path GPBs draft reasons paper

    See documents

  • 12 Dec 2011

    Completed

    Correspondence on draft determinations for GPBs

    See documents

  • 21 Nov 2011

    Completed

    Initial default price-quality path for gas pipeline businesses – Draft reasons paper

    See documents

  • 10 Oct 2011

    Completed

    Cross-submissions on setting of starting prices for gas pipeline businesses under the initial default price-quality path

    See documents

  • 29 Sep 2011

    Completed

    Submissions on setting of starting prices for gas pipeline businesses under the initial default price-quality path

    See documents

  • 22 Aug 2011

    Completed

    Setting of starting prices for gas pipeline businesses under the initial default price-quality path - Discussion paper

    See documents

  • 06 Jul 2011

    Completed

    Information request for starting price adjustments

    See documents

  • 17 Jun 2011

    Completed

    Submissions on default price-quality path for gas pipeline businesses draft information requests and process update

    See documents

  • 13 Jun 2011

    Completed

    Cross-submissions on initial default price-quality path for gas pipelines businesses discussion paper

    See documents

  • 03 Jun 2011

    Completed

    Draft information requests and process update – Consultation paper

    See documents

  • 30 May 2011

    Completed

    Submissions on initial default price-quality path for gas pipelines businesses discussion paper

    See documents

  • 01 Apr 2011

    Completed

    Initial default price-quality path for gas pipelines businesses discussion paper

    See documents

  • 21 Dec 2010

    Completed

    Submission on starting price adjustment process for default price-quality paths

    See documents

  • 10 Nov 2010

    Completed

    Starting price adjustments – Discussion paper

    See documents

  • 10 Sep 2010

    Completed

    Submissions on starting price adjustments for default price-quality paths discussion paper

    See documents

  • 18 Aug 2010

    Completed

    Correspondence – Gas default price-quality path

    See documents

  • 12 Aug 2010

    Completed

    Submissions on input methodologies gas pipeline services draft reasons and determination

    See documents

  • 28 Jun 2010

    Completed

    Cross-submissions on starting price adjustments for default price-quality paths discussion paper

    See documents

  • 30 May 2010

    Completed

    Cross-submission to submissions on the initial gas default price-quality path issues paper

    See documents

  • 18 May 2010

    Completed

    Submissions on the initial gas default price-quality path issues paper

    See documents

  • 10 May 2010

    Completed

    Submissions on the Form of Control - Initial gas default price-quality path issues paper

    See documents

  • 12 Apr 2010

    Completed

    Initial gas default price-quality path issues paper

    See documents

  • 09 Oct 2009
  • 11 Aug 2009

    Completed

    Submissions on the initial gas default price-quality path process paper

    See documents

  • 10 Aug 2009

    Completed

    Request for confirmation regarding Vector's methodology for demonstrating compliance with section 55F(2)

    See documents

  • 24 Jul 2009

    Completed

    Initial gas default price-quality path – Process paper

    See documents

Show all