The latest consolidated version of the fibre input methodologies was published on 21 December 2021 and incorporates the amendments made up to that date.

Here you can see the decisions made and the process of how we got to those decisions.


This view shows the latest stage in the project. Click on the circled dates to see details. Navigate to other months, or scroll down, to see all stages.

Note: these dates are indicative only and are subject to change.

  • 21 Dec 2021

    Completed

    Consolidated Fibre Input Methodologies Determination published

    See documents

  • 29 Nov 2021

    Completed

    Final decisions November 2021 Input Methodologies amendments due

    See documents

  • 28 Oct 2021

    Completed

    Cross-submissions on Revised input methodology amendments draft decisions due

  • 21 Oct 2021

    Completed

    Submissions on Revised input methodology amendments draft decisions due

    See documents

  • 30 Sep 2021

    Completed

    Revised input methodology amendments draft decisions

    See documents

  • 30 Sep 2021

    Completed

    Cross-submissions on input methodology amendments due

    See documents

  • 29 Sep 2021

    Completed

    Final input methodology amendments – Capex IM

    See documents

  • 23 Sep 2021
  • 16 Sep 2021

    Completed

    Submissions on input methodology amendments due

    See documents

  • 31 Aug 2021

    Completed

    Draft decision for input methodology amendments due

    See documents

  • 19 Aug 2021
  • 22 Jul 2021

    Completed

    Cross-submissions on potential November 2021 Input Methodologies amendments draft decisions due

    See documents

  • 08 Jul 2021

    Completed

    Cross-submissions on potential August 2021 Input Methodologies amendments draft decisions due

  • 08 Jul 2021

    Completed

    Submissions on potential November 2021 Input Methodologies amendments draft decisions due

    See documents

  • 24 Jun 2021

    Completed

    Submissions on potential August 2021 Input Methodologies amendments draft decisions due

    See documents

  • 27 May 2021

    Completed

    Draft decisions for Input Methodologies amendments published

    See documents

  • 30 Apr 2021
  • 30 Mar 2021

    Completed

    Letter to stakeholders on the impact of the COVID-19 pandemic on the cost of capital IM for fibre

    See documents

  • 03 Nov 2020

    Completed

    Final IM decisions reasons paper and final determination for financial loss asset provisions due

    See documents

  • 28 Oct 2020

    Completed

    Incorporation of accounting standard by reference into Fibre Input Methodologies Determination 2020

    See documents

  • 13 Oct 2020

    Completed

    Email to industry – Main final fibre input methodologies decision

    See documents

  • 13 Oct 2020

    Completed

    Main final decisions – reasons paper and final determination (excluding financial loss asset)

    See documents

  • 01 Oct 2020

    Completed

    Cross-submissions on second consultation paper on financial loss asset and associated provisions for Draft Determination due

    See documents

  • 10 Sep 2020

    Completed

    Submissions on second consultation paper on financial loss asset and associated provisions for Draft Determination due

    See documents

  • 08 Sep 2020

    Completed

    Cross-submissions on main consultation paper (connection capex and two-step cost allocation) due

  • 03 Sep 2020

    Completed

    Cross-submissions on main consultation paper and updated Draft Determination (excluding financial loss asset) due

    See documents

  • 28 Aug 2020

    Completed

    Chorus submission on main consultation paper (connection capex and two-step cost allocation)

    See documents

  • 20 Aug 2020

    Completed

    Submissions on Dr Martin Lally expert report

    See documents

  • 13 Aug 2020

    Completed

    Further consultation draft (initial value of financial loss asset) due

    See documents

  • 13 Aug 2020

    Completed

    Submissions on main consultation paper and updated Draft Determination (excluding financial loss asset) due

    See documents

  • 23 Jul 2020

    Completed

    Main consultation paper and updated Draft Determination (excluding financial loss asset) due

    See documents

  • 10 Jul 2020

    Completed

    Questions to which Dr Lally’s report (published on 27 May 2020) responds

    See documents

  • 10 Jul 2020

    Completed

    Change to further consultation process and publication dates

    See documents

  • 19 Jun 2020

    Completed

    Cross-submissions on Regulatory processes and rules draft decision due

    See documents

  • 29 May 2020

    Completed

    Submissions on Regulatory processes and rules draft decision due

    See documents

  • 27 May 2020

    Completed

    Dr Martin Lally expert report published

    See documents

  • 20 May 2020
  • 02 Apr 2020
  • 02 Apr 2020

    Completed

    Regulatory processes and rules draft decision published

    See documents

  • 17 Feb 2020

    Completed

    Cross-submissions on draft decision and determination due

    See documents

  • 28 Jan 2020

    Completed

    Submissions on draft decision and determination due

    See documents

  • 12 Dec 2019
  • 11 Dec 2019
  • 19 Nov 2019
  • 24 Oct 2019

    Completed

    Letter to stakeholders – Chorus’ independent expert for first regulatory period

    See documents

  • 16 Sep 2019

    Completed

    Regulatory processes and rules input methodology cross-submissions published

    See documents

  • 10 Sep 2019

    Completed

    Regulatory processes and rules input methodology submissions published

    See documents

  • 29 Aug 2019
  • 19 Aug 2019

    Completed

    Regulatory processes and rules input methodology topic paper published

    See documents

  • 09 Aug 2019

    Completed

    Cross-submissions received on fibre regulation emerging views paper – Cost of capital and risk

    See documents

  • 31 Jul 2019

    Completed

    Cross-submissions received on fibre regulation emerging views paper – general

    See documents

  • 16 Jul 2019

    Completed

    Submissions received on fibre regulation emerging views paper

    See documents

  • 01 Jul 2019
  • 01 Jul 2019
  • 21 May 2019
  • 04 Mar 2019
  • 01 Feb 2019

    Completed

    Cross-submissions received on new regulatory framework for fibre

    See documents

  • 21 Dec 2018

    Completed

    Submissions received on new regulatory framework for fibre

    See documents

  • 10 Dec 2018
  • 23 Nov 2018

    Completed

    Response to request for extension to implementation date

    See documents

  • 20 Nov 2018

    Completed

    Request for extension to implementation date

    See documents

  • 19 Nov 2018
  • 09 Nov 2018
Show all