Input methodologies for fibre are the rules, requirements and processes that we are required to develop under Part 6 of the Telecommunications Act. We are currently developing these fibre input methodologies.
Input methodologies (IMs) are the rules, requirements and processes that underpin regulation under Part 6 of the Telecommunications Act. We will have to apply the IMs when we set price-quality paths and set information disclosure requirements. Regulated businesses will also be required to apply the IMs.
The purpose of IMs is to promote certainty for regulated fibre service providers, access seekers, and end-users in relation to the rules, requirements, and processes applying to the regulation, or proposed regulation, of fibre fixed line access services.
This view shows the latest stage in the project. Click on the circled dates to see details. Navigate to other months, or scroll down, to see all stages.
Note: these dates are indicative only and are subject to change.
-
30 Mar 2021
-
03 Nov 2020
Completed
Final IM decisions reasons paper and final determination for financial loss asset provisions due
-
28 Oct 2020
Completed
Incorporation of accounting standard by reference into Fibre Input Methodologies Determination 2020
-
13 Oct 2020
Completed
Email to industry – Main final fibre input methodologies decision
-
13 Oct 2020
Completed
Main final decisions – reasons paper and final determination (excluding financial loss asset)
-
01 Oct 2020
Completed
Cross-submissions on second consultation paper on financial loss asset and associated provisions for Draft Determination due
-
10 Sep 2020
Completed
Submissions on second consultation paper on financial loss asset and associated provisions for Draft Determination due
-
08 Sep 2020
Completed
Cross-submissions on main consultation paper (connection capex and two-step cost allocation) due
-
03 Sep 2020
Completed
Cross-submissions on main consultation paper and updated Draft Determination (excluding financial loss asset) due
-
28 Aug 2020
Completed
Chorus submission on main consultation paper (connection capex and two-step cost allocation)
-
20 Aug 2020
Completed
Submissions on Dr Martin Lally expert report
-
13 Aug 2020
Completed
Submissions on main consultation paper and updated Draft Determination (excluding financial loss asset) due
-
13 Aug 2020
Completed
Further consultation draft (initial value of financial loss asset) due
-
23 Jul 2020
Completed
Main consultation paper and updated Draft Determination (excluding financial loss asset) due
-
10 Jul 2020
Completed
Change to further consultation process and publication dates
-
10 Jul 2020
Completed
Questions to which Dr Lally’s report (published on 27 May 2020) responds
-
19 Jun 2020
Completed
Cross-submissions on Regulatory processes and rules draft decision due
-
29 May 2020
Completed
Submissions on Regulatory processes and rules draft decision due
-
27 May 2020
Completed
Dr Martin Lally expert report published
-
20 May 2020
Completed
Process update paper published
-
02 Apr 2020
Completed
Industry update
-
02 Apr 2020
Completed
Regulatory processes and rules draft decision published
-
17 Feb 2020
Completed
Cross-submissions on draft decision and determination due
-
28 Jan 2020
Completed
Submissions on draft decision and determination due
-
12 Dec 2019
Completed
Chorus Capex IM workshop
-
11 Dec 2019
Completed
Draft determination due
-
19 Nov 2019
Completed
Draft decision due
-
24 Oct 2019
Completed
Letter to stakeholders – Chorus’ independent expert for first regulatory period
-
16 Sep 2019
Completed
Regulatory processes and rules input methodology cross-submissions published
-
10 Sep 2019
Completed
Regulatory processes and rules input methodology submissions published
-
29 Aug 2019
Completed
Letter to stakeholders
-
19 Aug 2019
Completed
Regulatory processes and rules input methodology topic paper published
-
09 Aug 2019
Completed
Cross-submissions received on fibre regulation emerging views paper – Cost of capital and risk
-
31 Jul 2019
Completed
Cross-submissions received on fibre regulation emerging views paper – general
-
16 Jul 2019
Completed
Submissions received on fibre regulation emerging views paper
-
01 Jul 2019
Completed
Supplementary submission question
-
01 Jul 2019
Completed
Emerging views workshop material
-
21 May 2019
Completed
Emerging views paper published
-
04 Mar 2019
Completed
Process update
-
01 Feb 2019
Completed
Cross-submissions received on new regulatory framework for fibre
-
21 Dec 2018
Completed
Submissions received on new regulatory framework for fibre
-
10 Dec 2018
Completed
Stakeholder workshop
-
23 Nov 2018
Completed
Response to request for extension to implementation date
-
20 Nov 2018
Completed
Request for extension to implementation date
-
19 Nov 2018
Completed
Notice of intention published
-
09 Nov 2018
Completed
New regulatory framework for fibre
-
09 Nov 2018
-