Electricity demand in the region is increasing so the network also requires reinforcement.

Transpower is planning a major capex proposal to invest and maintain a reliable electricity supply in the Bombay-Otahuhu region.

On 18 January 2019, Transpower and the Commission agreed to a consultation programme, approval timeframe and approach to considering non-Transpower solutions. As Transpower develops the project, Transpower and the Commission will review the timeframes as necessary.

This view shows the latest stage in the project. Click on the circled dates to see details. Navigate to other months, or scroll down, to see all stages.

Note: these dates are indicative only and are subject to change.

  • 19 Mar 2021

    Final decision due

  • 22 Jan 2021

    Cross-submissions on draft decision due

  • 17 Dec 2020
  • 26 Nov 2020
  • 15 May 2020
  • 24 Jul 2019

    Completed

    Request for proposals for non-transmission solutions

  • 22 Feb 2019

    Completed

    Long list consultation

Show all