This page was updated8 days ago
On 27 November 2019 we set the third default price-quality path (DPP) for the 17 electricity distributors subject to price-quality regulation.
These price-quality paths will apply for the period 1 April 2020 to 31 March 2025. Aurora Energy is currently on a Customised Price-quality Path (CPP) which expires 31 March 2026. Previously in this DPP reset, Wellington Electricity were on a CPP (expired 31 March 2021) as too were Powerco (expired 31 March 2023).
In July 2021, Centralines underwent a process to become completely consumer owned by changing its trust deed to make all trustees consumer elected. This made Centralines DPP exempt and were no longer price-quality regulated.**
Distributors subject to the 2020-2025 default price-quality path
-
Alpine Energy
Aurora Energy
Centralines**
Eastland Networks
Electricity Ashburton
-
Electricity Invercargill
Horizon Energy
The Lines Company
Network Tasman
-
Nelson Electricity
Orion
OtagoNet Joint Venture
Powerco*
-
Top Energy
Unison Networks
Vector
Wellington Electricity*
This view shows the latest stage in the project. Click on the circled dates to see details. Navigate to other months, or scroll down, to see all stages.
Note: these dates are indicative only and are subject to change.
-
19 Sep 2024
-
08 Aug 2024
Completed
Final decision on Wellington Electricity’s unforeseen capex reopener
-
22 Jul 2024
Completed
Approval letter – Powerco innovation project allowance
-
22 Jul 2024
Completed
Approval letter – Orion innovation project allowance ViSION project
-
03 Jul 2024
Completed
Draft decision on Unison Networks unforeseen capex reopener
-
03 Jul 2024
Completed
Orion and Wellington Electricity Resi-Flex innovation project allowance – Application
-
03 Jul 2024
Completed
Wellington Electricity innovation project allowance – Application
-
04 Jun 2024
Completed
Submissions on Wellington Electricity’s unforeseen capex reopener draft decision due
-
22 May 2024
Completed
Unison Networks Limited unforeseen major capex reopener application
-
21 May 2024
Completed
Draft decision on Wellington Electricity unforeseen capex reopeners
-
16 Feb 2024
Completed
Wellington Electricity unforeseen capex reopener applications
-
05 Feb 2024
Completed
Report – Vector PRISMED innovation project allowance
-
22 Nov 2023
Completed
Approval letter – Vector PRISMED innovation project allowance
-
15 Nov 2023
Completed
Correspondence on potential catastrophic event reopener applications relating to cyclone Gabrielle and Auckland floods
-
13 Nov 2023
Completed
Amendment to DPP for electricity distribution businesses 2020-2025 (Innovation Project Allowance Criteria)
-
01 Mar 2023
Completed
Amendment to DPP for electricity distribution businesses 2020-2025 (Compliance statement due date)
-
28 Mar 2022
Completed
Correspondence on Orion’s June 2021 Innovation Allowance Application
-
04 Mar 2022
Completed
Final decision on Unison’s capex reopener application
-
15 Dec 2021
Completed
Submissions on Unison’s capex reopener draft decision due
-
01 Dec 2021
Completed
Draft decision on Unison’s capex reopener application
-
22 Dec 2020
Completed
Final Aurora QSV decision due
-
30 Nov 2020
Completed
Submissions on QSV draft decision due
-
26 Nov 2020
Completed
Publication of Wellington Electricity CPP to DPP
-
12 Nov 2020
Completed
Draft decision on Aurora's Quality Standard Variation (QSV)
-
10 Aug 2020
Completed
Orion third party financing of new investment contract letter
-
31 Jul 2020
Completed
Feedback on our processes to reset price-quality paths
-
30 Jul 2020
Completed
Aurora’s Quality Standard Variation request published
-
08 Jun 2020
Completed
Open letter seeking feedback on our processes to reset price-quality paths
-
20 May 2020
Completed
Publication of EDB DPP3 consolidated determination
-
30 Mar 2020
Completed
Final decision – Discount error correction
-
12 Mar 2020
Completed
Submissions on draft decision – Discount error correction
-
28 Feb 2020
Completed
Application of reliability normalisation and assessment – Final DPP3 demonstration model
-
27 Feb 2020
Completed
Draft decision – Discount error correction
-
27 Nov 2019
Completed
Final decision due
-
25 Oct 2019
Completed
Cross-submissions on EDB DPP3 SAIFI consultation paper due
-
18 Oct 2019
Completed
Submissions due on EDB DPP3 SAIFI consultation paper
-
17 Oct 2019
Completed
Correspondence between the ENA and Commission on the WACC estimate and CPI forecasts for DPP3
-
16 Oct 2019
Completed
Cross-submissions due on companion paper to updated models
-
09 Oct 2019
Completed
Submissions due on companion paper to updated models
-
07 Oct 2019
Completed
EDB DPP – SAIFI process
-
07 Oct 2019
Completed
EDB DPP3 – Recording of successive interruptions for SAIFI
-
25 Sep 2019
Completed
Companion paper to updated models due
-
16 Aug 2019
Completed
Targeted quality workshop
-
12 Aug 2019
Completed
Cross-submissions due on draft decision
-
18 Jul 2019
Completed
Submissions due on draft decisions
-
28 Jun 2019
Completed
Notice to supply information for 2020 DPP reset under section 53ZD
-
21 Jun 2019
Completed
Additional models to support the draft decision
-
29 May 2019
Completed
Draft decision due
-
29 May 2019
Completed
Additional material provided by external parties for consultation on draft decision
-
29 Mar 2019
Completed
Feedback on Application for accelerated depreciation for EDB DPP3 published
-
08 Mar 2019
Completed
Second workshop on EDB DPP3 reset
-
27 Feb 2019
Completed
First workshop on EDB DPP3 reset
-
05 Feb 2019
Completed
Cross-submissions on EDB DPP reset issues paper published
-
31 Jan 2019
Completed
Cross-submissions on issues paper due
-
21 Dec 2018
Completed
Submissions on issues paper
-
15 Nov 2018
Completed
Issues paper due
-
15 Nov 2018
Completed
Notice to supply quality of service information for DPP3 reset
-
05 Nov 2018
Completed
DPP knowledge sharing session
-
06 Sep 2018
Completed
Process update paper
-
17 Jul 2018
Completed
Submissions on process due
-
14 Jun 2018
Completed
Process paper due
Related projects
IM amendments for EDB DPP
As part of our process of setting the default price-quality path (DPP) for electricity distribution businesses from 1 April 2020, we may consider amendments to the input methodologies for electricity distribution services necessary to implement this DPP and future price-quality paths.