Orion's network area is bordered by the Rakaia and Waimakariri rivers and stretches from the Southern Alps to Banks Peninsula. Orion formally applied to the Commission on 20 February 2013 for a customised price-quality path (CPP).

Orion proposed to increase its maximum average prices and reduce its required quality standards over the five years commencing 1 April 2014. Orion’s proposal was intended to address the impact of the Canterbury earthquakes, including the recovery of additional costs, lower than expected revenues, and to fund future investment in its network.

This view shows the latest stage in the project. Click on the circled dates to see details. Navigate to other months, or scroll down, to see all stages.

Note: these dates are indicative only and are subject to change.

  • 05 Aug 2014

    Completed

    Feedback received on process to set the customised price-quality path for Orion

    See documents

  • 04 Mar 2014

    Completed

    Request for feedback on our process to set the customised price-quality path for Orion

    See documents

  • 19 Dec 2013

    Completed

    Response to Orion request for information about Final Decision

    See documents

  • 29 Nov 2013

    Completed

    Final Decision on Orion’s CPP proposal

    See documents

  • 29 Nov 2013

    Completed

    Expert reports released with final decision on Orion’s CPP proposal

    See documents

  • 29 Nov 2013
  • 06 Nov 2013

    Completed

    Consultation on Proposed Approach to Specification of Controllable Opex

    See documents

  • 18 Oct 2013

    Completed

    Section 53ZD notice to supply information

    See documents

  • 09 Sep 2013

    Completed

    Response to Orion request for information about draft decision

    See documents

  • 04 Sep 2013

    Completed

    Draft determination on Orion's CPP proposal

    See documents

  • 14 Aug 2013

    Completed

    Expert reports released with draft decision on Orion's CPP proposal

    See documents

  • 14 Aug 2013
  • 07 Jun 2013
  • 01 May 2013
  • 19 Apr 2013
  • 18 Apr 2013

    Completed

    Orion customised price-quality path proposal

    See documents

Show all